How might we clean the process tanks of water reclamation plants without requiring human entry to improve safety and reduce reliance on manual labour?
Challenge Owners
Background & Current Practice
PUB’s water reclamation plants have treatment processes that involve large tanks with restricted access for safety purposes. Currently, these process tanks are cleaned two to three times a year, and workers must endure confined space conditions to carry out tank cleaning works. The current method requires up to six workers to concurrently perform cleaning works by water-jetting and dispose dislodged sludge materials for an estimated duration of six working days for each tank. The clean tanks are inspected and repaired before re-commissioning.
The table below explains the current workflow for the maintenance of process tanks, which includes both cleaning and repair works:
Step | Description | Duration |
---|---|---|
1 | Isolate and drain process tank. Apply Log Out Tag Out (LOTO) | 1 day |
2 | Set-up confined space work equipment | 1 day |
3 | Deploy workers to clean the top deck of the tank. | 2 days |
4 | Deploy workers to clean the bottom deck of the tank |
2 days |
5 | Perform scheduled repair works such as scrapper replacement, conveyor motor repair, conveyor belt repair |
~10 days |
6 | Remove confined space work equipment and re-commission tank. |
1 day |
For sedimentation tanks found in Changi Water Reclamation Plant, scrappers are used to remove settled sludge by sweeping them into a sludge hopper for disposal. However, over time, hardened sludge, string-like debris, and other wastes accumulate on the tank walls, floors, and scrappers, which cannot be removed by the scrapper. Additionally, the scrappers are unable to sweep the entire breadth of the tank, resulting some dead zones that accumulate settled sludge. Certain tanks also have blind corners and uneven terrain, which require workers to don additional personal protective equipment, such as safety harness, as safeguarding measures.
We are interested in robotics systems that can clean our water reclamation plant process tanks without requiring human entry. We seek solutions that can potentially eliminate manual labour from the tank cleaning process, thus eliminating any safety risk associated with manual labour.
The robotics system shall be able to perform the following tasks:
For the pilot project, we will first focus on the cleaning of primary sedimentation tanks. We plan to scale this method for other process tanks such secondary sedimentation tanks and bioreactors basin. There are more than 60 process tanks within one plant that could benefit from the solution.
The proposed solution should be able to accommodate the following developments in the future:
Besides robotics systems, we are open to hard automation solutions that are cost-effective, easy to maintain and scalable across the process tanks.
A. System Requirements
B. Cleaning and Handling of Sludge
A. Tank Cleaning Maintenance Work.
John is responsible for cleaning the Sedimentation Tanks at Changi Water Reclamation Plant on a monthly basis, where each tank is typically cleaned once every 4-6 months. Unfortunately, this task exposes John to hazardous conditions such as confined spaces and working at heights. To address this issue, robotic solutions can be implemented. By using a remotely controlled robot to clean the tank, John can minimize his need to enter the tank himself and human entry into the tanks is only required for the deployment and retrieval of the robot. This approach significantly reduces the risks associated with the hazardous conditions, creating a safer working environment for John and his colleagues.
By the end of the pilot, the project should aim to develop a site-tested prototype that can effectively and safely clean at least one type of process tank found in the water reclamation plant, without requiring human entry into the tank. A redesigned cleaning operation plan as well as a method to properly dispose loose sludge should also be established. After each deployment, a report documenting the cleaned tank is generated.
The pilot project is to be completed within a period of 18 months. Below are the suggested project scope and timeline:
Below is a guide for the timeline and activities to be included in your proposal. Please note that the timeline and activities may vary depending on the type and maturity of the technology.
If the pilot is successful, PUB would be interested to deploy the solution through a service model where the equipment is owned, operated, and maintained by the company.
Challenge Owners
Background & Current Practice
PUB’s water reclamation plants have treatment processes that involve large tanks with restricted access for safety purposes. Currently, these process tanks are cleaned two to three times a year, and workers must endure confined space conditions to carry out tank cleaning works. The current method requires up to six workers to concurrently perform cleaning works by water-jetting and dispose dislodged sludge materials for an estimated duration of six working days for each tank. The clean tanks are inspected and repaired before re-commissioning.
The table below explains the current workflow for the maintenance of process tanks, which includes both cleaning and repair works:
Step | Description | Duration |
---|---|---|
1 | Isolate and drain process tank. Apply Log Out Tag Out (LOTO) | 1 day |
2 | Set-up confined space work equipment | 1 day |
3 | Deploy workers to clean the top deck of the tank. | 2 days |
4 | Deploy workers to clean the bottom deck of the tank |
2 days |
5 | Perform scheduled repair works such as scrapper replacement, conveyor motor repair, conveyor belt repair |
~10 days |
6 | Remove confined space work equipment and re-commission tank. |
1 day |
For sedimentation tanks found in Changi Water Reclamation Plant, scrappers are used to remove settled sludge by sweeping them into a sludge hopper for disposal. However, over time, hardened sludge, string-like debris, and other wastes accumulate on the tank walls, floors, and scrappers, which cannot be removed by the scrapper. Additionally, the scrappers are unable to sweep the entire breadth of the tank, resulting some dead zones that accumulate settled sludge. Certain tanks also have blind corners and uneven terrain, which require workers to don additional personal protective equipment, such as safety harness, as safeguarding measures.
We are interested in robotics systems that can clean our water reclamation plant process tanks without requiring human entry. We seek solutions that can potentially eliminate manual labour from the tank cleaning process, thus eliminating any safety risk associated with manual labour.
The robotics system shall be able to perform the following tasks:
For the pilot project, we will first focus on the cleaning of primary sedimentation tanks. We plan to scale this method for other process tanks such secondary sedimentation tanks and bioreactors basin. There are more than 60 process tanks within one plant that could benefit from the solution.
The proposed solution should be able to accommodate the following developments in the future:
Besides robotics systems, we are open to hard automation solutions that are cost-effective, easy to maintain and scalable across the process tanks.
A. System Requirements
B. Cleaning and Handling of Sludge
A. Tank Cleaning Maintenance Work.
John is responsible for cleaning the Sedimentation Tanks at Changi Water Reclamation Plant on a monthly basis, where each tank is typically cleaned once every 4-6 months. Unfortunately, this task exposes John to hazardous conditions such as confined spaces and working at heights. To address this issue, robotic solutions can be implemented. By using a remotely controlled robot to clean the tank, John can minimize his need to enter the tank himself and human entry into the tanks is only required for the deployment and retrieval of the robot. This approach significantly reduces the risks associated with the hazardous conditions, creating a safer working environment for John and his colleagues.
By the end of the pilot, the project should aim to develop a site-tested prototype that can effectively and safely clean at least one type of process tank found in the water reclamation plant, without requiring human entry into the tank. A redesigned cleaning operation plan as well as a method to properly dispose loose sludge should also be established. After each deployment, a report documenting the cleaned tank is generated.
The pilot project is to be completed within a period of 18 months. Below are the suggested project scope and timeline:
Below is a guide for the timeline and activities to be included in your proposal. Please note that the timeline and activities may vary depending on the type and maturity of the technology.
If the pilot is successful, PUB would be interested to deploy the solution through a service model where the equipment is owned, operated, and maintained by the company.